Example RAMS · Solar

Solar Panel Installation — Warehouse Roof

A sample Risk Assessment and Method Statement showing the structure and level of detail RAMS Pal produces. The details below are illustrative — your own document is built from your own answers.

Issued 27 Aug 2026 · Last reviewed 30 September 2026

Contractor in hi-vis reviewing job paperwork on a tablet on a solar rooftop at sunset
Client
Midland Logistics Ltd
Site
Unit 4, Kingsbury Industrial Estate, Birmingham
Prepared by
James Carter
Supervisor
James Carter
Operatives
4
Review date
27 Feb 2027

Scope of works

Installation of 24 roof-mounted photovoltaic panels, mounting rails, DC cabling and a string inverter to the north elevation of an occupied distribution warehouse. Roof access will be gained via a MEWP with a temporary edge protection system to the working area.

Risk assessment

Each hazard is rated on a 5×5 matrix, likelihood × severity, before and after the control measures: 1–6 is low, 8–12 medium and 15–25 high. These are the rows RAMS Pal generates for these hazards, highest initial risk first, and every one is edited to fit the actual job before the document is issued.

HazardWho is harmedInitial ratingControl measuresResidual rating
Working at heightOperatives, persons below204×5Work planned to avoid height where reasonably practicable. Access equipment selected for the task and inspected before use. Collective protection (guard rails, edge protection) before personal protection. Where fall arrest is required, harness and lanyard worn with a suitable anchor point. Exclusion zone established below the work area. Work stopped in high winds or heavy rain.51×5
Electrical shockOperatives153×5Safe isolation procedure followed: identify, isolate, secure with lock-off and tag, prove the tester, test dead, re-prove the tester. Work carried out dead wherever reasonably practicable. 110V CTE tools used in preference to 230V. All portable equipment within test date and visually inspected before use.41×4
Falling objectsOperatives, persons below, public123×4Exclusion zone established and signed below all overhead work. Toe boards and brick guards fitted to scaffolds. Tools tethered when used at height. Materials raised and lowered by hoist or rope, never dropped or thrown.41×4
Manual handlingOperatives124×3Mechanical aids used where available. Loads assessed before lifting; two-person lift for awkward or heavy items. Route checked and cleared before carrying. Operatives briefed on safe lifting technique. Loads broken down where practicable.42×2
Adverse weatherOperatives93×3Forecast checked each morning before work at height begins. Work at height stopped in wind speeds above the equipment manufacturer's limit, and in ice, heavy rain or lightning. Surfaces checked for ice before access. Hydration and shade provided in hot weather.31×3

PPE required

  • Safety helmet with chinstrap
  • Hi-vis vest
  • Safety boots
  • Gloves
  • Eye protection
  • Full body harness

Plant and equipment

  • MEWP (Genie GS-1932)
  • Power tools (110V)
  • Hand tools
  • Lifting equipment
  • Harness and lanyard

Method statement

  1. 1Attend site and complete the site induction with the client's representative.
  2. 2Confirm the work area, welfare facilities and access arrangements.
  3. 3Establish an exclusion zone at ground level beneath the working area.
  4. 4Inspect access equipment and record pre-use checks.
  5. 5Isolate electrical systems where required and apply locks and tags.
  6. 6Position the MEWP on firm, level ground and deploy outriggers.
  7. 7Complete the mounting rail and panel installation working from the ridge outwards.
  8. 8Inspect the completed work and carry out electrical testing.
  9. 9Remove waste, tools and materials from the roof.
  10. 10Hand the work area back to the client and complete sign-off.

This example illustrates the RAMS for Solar Installers page, which explains what a RAMS for this work has to show and the legislation it cites. New to RAMS? Start with what a RAMS document is.

RAMS Pal is a documentation support tool. Generated content must be reviewed and adapted to the actual work, site conditions, workforce, equipment and applicable health & safety requirements.